This synthesis seeks to determine the elements of the open-book process that contribute to a mutual agreement on a project’s construction price. A major difference between both construction manager/general contractor (CM/GC) and progressive design-build (PDB) and other public contracting methods is the ability to negotiate open-book pricing after the contract is awarded. That ability, coupled with early contractor involvement in the planning and design process, is a key benefit that a state department of transportation (DOT) can expect if it implements CM/GC, PDB, or both. The literature confirms this assertion; however, little, if anything, has been written about the mechanics of open-book negotiations.
The objective of this synthesis is to benchmark the state of the practice regarding the policies and procedures used by DOTs to negotiate the construction pricing on CM/GC and PDB projects using open-book approaches. The synthesis documents agency practices and specifications regarding open-book estimating and negotiations and the successes and challenges of both. To accomplish this task, a comprehensive review of the alternative contracting literature was conducted and used to produce a nationwide survey of DOTs, which received responses from 42 DOTs, yielding an 82% response rate. The survey results were analyzed by conducting a content analysis of DOT alternative project delivery guidelines and manuals and DOT CM/GC and PDB solicitation documents from 27 DOTs. Finally, interviews with the participants of nine case examples (six CM/GC and three PDB projects) were conducted. In two of the case examples, an off-ramp was executed when the amount proposed by the contractor and validated by the independent cost estimator (ICE) exceeded the available funding.
To use open-book negotiation of construction pricing, the DOT usually needs the authority to implement CM/GC and/or PDB. The statutes from 36 states were reviewed to better understand the role of enabling legislation on this topic. A key finding showed that some states had interpreted their existing alternative legislation to cover CM/GC and/or PDB and that specific enabling legislation was not necessarily required. This finding was particularly true for PDB in which a number of DOTs had chosen to implement PDB under their current design-build (DB) authority without seeking specific authorization for PDB.
The synthesis provides a synopsis of the state of the practice by assessing the facts gathered from the literature review, survey, and case examples. The synthesis team found that DOTs have utilized various methods, tools, manuals, guidance, and specifications to implement open-book negotiations on CM/GC and PDB projects. The major findings of the synthesis are summarized in the following section. Findings and recommendations for future research are discussed in more detail in Chapter 5.
Each DOT defines and controls its own open-book negotiation process and can dictate the required documentation needed from the contractor to achieve a fair and reasonable GMP. However, the synthesis team found that many DOTs are not publishing the details of how they want to conduct open-book negotiations. Nevertheless, the open-book process has demonstrated itself to lead to agreement on GMPs without a detailed description. That fact can be attributed to the dialogue on scope, risk, market costs, and schedule that is inherently invoked when the contractor collaborates with the owner during the project’s design process.